THE CROWN GREENS - SITE PROGRESS AS ON 09 MARCH 2016

TOWER NT1 - 17TH SLAB (16TH FLOOR SLAB) CASTED ON 09 MARCH 2016

TOWER NT2 - 18TH SLAB (17TH FLOOR SLAB) CASTED ON 11 MARCH 2016

BLOCK MASONRY WORK HAS BEEN COMPLETED OF THE FLAT AREA

TOWER NT1 - 11TH FLOOR